Enter pay rates for resources

​Costs for resources is calculated based on regular and overtime rates or on the per-use cost you enter, or you can enter a one-time assignment cost.

Enter or change resource rates

  1. On the View menu, click Resource Sheet.
  2. On the View menu, point to Table, and then click Entry.
  3. In the Standard Rate, type the resource rates.

Notes

  • Application can calculates cost totals as soon as rate-based resources and resources with per-use costs are assigned to tasks.
  • Changing the resource standard rate also effects the cost of a task which is 100 percent complete and which has the same resource assigned to it.
  1. On the View menu, click Resource Sheet.
  2. On the View menu, point to Table, and then click Entry.
  3. In the Cost Per Use  column, type the cost per use.

Application calculate cost totals as soon as rate-based resources and resources with per-use costs are assigned to tasks.​